Update from Stirling Council on the work to repair Branshogle Bridge.
Headlines:
The project has been delayed by 1 week. The new reopening date is the 12th December
Where are we?
Kerbing is completed. There have been some unexpected obstructions which delayed the installation of the safety barriers. A solution has been found and additional ground works have commenced to ensure that the barriers are installed safely and are compliant with standards.
What’s Next?
Completion of essential ground works; 2nd– 8th December
Road Surfacing to begin 7th Dec – 9th December
Site clearance, road sweeping, new road markings, temporary lights set up; 10 -11th December
Road will be reopened to traffic under 24/7 temporary traffic lights from 12th December as installation of barriers is completed.